reports from laverdad.es, regarding Trampolin Hills Campos del Rio Murcia
click here for the report in Spanish
Translation of article.
The City Council takes a month to Grupo Trampolínto correct 5 deficiencies in its resort The plenary agreed to the adoption of the draft interim repairs that will allow the construction of 2,500 homes
A month. That is the term that the city of Campos del Rio has given Grupo Trampolín five to remedy deficiencies in the project for which aims to build 2,500 homes and a golf course on the site of El Barril.
The opening of this term was the main novelty of a plenary session that was described as "pantomime" by the president of Grupo Trampolín, Antonio Martínez.
According to Martinez, the deal that were raised yesterday and which appear in a report dated last-day 10 - the technical architect of the municipality, which Grupo Trampolín was not aware until Tuesday and that in turn runs counter to other-dated at this time February-signed also by the technical architect, Antonio Plaza, which gave the green light to the project without hesitation.
Martinez said that his company is able to remedy the deficiencies within 30 days of the project, which would lead to the conclusion of a separate House and the referral to the Directorate General of Urban Planning of the project to give free rein to the building, whose preliminary and can be seen at the site of The Barrel.
The defects seen the draft report in the trade center on the descuadre of areas to urbanize, which in turn would force the correct criteria floor. In addition, it also calls for building as the disaffection of a cattle track, the clear definition of the road system, the update of plans and define the removal of architectural barriers in public areas.
Funding to the edge Group president Grupo Trampolín said that delays in the approval of the project have already caused you to lose financing that the Fund had committed the Mediterranean for the complex, 'and we had to replace it with another private investor.This funding, however "is at risk due to the constant delays in the project," said Martinez.
Martinez denied that the bank guarantees of buyers has been performed in its entirety and put at 4 million euros for the balance that advances the group still manages to undertake the construction.
The Popular Party was again voted against the adoption and temporary-labeled in the words of its spokesman, Miguel Buendia, the House of absurdity. "We do not understand is that if you do this in one month, two if you count the time limit for public exposure to potential claims, we will have to return to vote. It is against common sense. "
The mayor, the socialist Miguel Navarro, requested the PP cooperation and invited him to join in future meetings to discuss the project with the autonomous region, in addition to describing the project as key to the town of just 2,000 inhabitants, exceeding the rampant crisis.