Hi Everyone
Thought that I would post some of the information that we received at La Tercia whilst we were in Murcia during February.
1. It has been previously suggest on the forum that the Master's Apartment lounge wall between lounge and adjacent bedroom had been moved by several inches. This is not the case and it remains as per plans.
2. Ground floor apartment gardens will be tiles to match the terrace surrounded by a low double wall which will be planted with shrubs. If grass is required this will be at extra cost.
3. Teresa, in UGR Sales Office at La Tercia, will post details of UGR's furniture packages upon request.
4. To establish exact room sizes in the apartments it is possible to apply a 1:100 scale to the drawings supplied with your contract
5. Phase 1 completion is still forecast as December 2007 and Phase 2 as June 2009
6. It was confirmed that the fridge and washing machine in the apartments will be white and not silver to match the stainless steel cooker. Silver appliances will be installed in the villas only
7. We were informed that the permission for the further 9 holes is imminent and that a Phase 3 is likely to be constructed on the far side of these new holes
8. It was established that for apartments, water and drainage will be available in both the kitchen and utility areas to allow for washing machine and dishwasher
9. It was confirmed that the Master's apartments will have an additional sink in the Utility area
10. UGR have decided to board in the apartment ground floor utility areas. This will be achieved by installing wooden horizontal beams with gaps for light and air.
11. We were informed that exterior changes, such as glazing in the utility area in the upper floors, will require the agreement of all apartment owners in the block
12. Whilst TV and phone connections were confirmed there was uncertainty about how the internet would be provided - it may be by satellite
13. It was established that the bedroom over looking the terrace is fitted with a window not patio doors
14. Master's apartments will have a breakfast bar between the kitchen and lounge - open plan effect - with a range of cupbards underneath on the kitchen side
15. The main road leading to the site is to be repaired and upgraded by all developers using it on completion of building works. Don't hold your breathe the MASA site is not due for completion for 10 years
16. The stone feature in the lounge is now optional - please let UGR know ASAP if you do not require it
17. The grass on the golf course will be laid during April
18. Shower screen will NOT be fitted
19. Solar heating for hot water will be supported by boilers in each apartment
20. The waste water from accommodation is to be recycled for use on the golf course - guaranteed not to smell. A massive water recycling plant is currently being constructed underground adjacent to the sales office.
21. There are no outlets for the cooling/heating systems in the apartment bathrooms and heated towel rails will not be fitted. The villas will have heated towel rails.
22. The current sales office building will remain becoming a machinery store for the golf course. The sales office will move to the commercial centre on the left hand side.
23. We expressed concern about lack of progress on Phase 1 commercial centre buildings. Assurances were given that work will progress shortly on completion of the surrounding apartment buildings.
I think that is all for now. We have information re restaurants which I will post later
Fiona & Pete